City crews work 12 hours a day to reopen Royal Palms Parkway ahead of schedule

An emergency structural repair was required, and the city’s Stormwater Pipe Crew finished the project in less than half the projected time.


  • By
  • | 8:30 a.m. October 2, 2021
Stormwater Pipe Crew: Kevin Nelson (Supervisor), Paul Bartnik, John Costa, Tim Lowe (Crew Leader), Andrew Torres, Steve Costa, Mark Johnson, Chris Bevacqua, and Angel Perez. Courtesy photo
Stormwater Pipe Crew: Kevin Nelson (Supervisor), Paul Bartnik, John Costa, Tim Lowe (Crew Leader), Andrew Torres, Steve Costa, Mark Johnson, Chris Bevacqua, and Angel Perez. Courtesy photo
  • Palm Coast Observer
  • News
  • Share

Thanks to city workers who stepped forward, a road project was completed ahead of schedule — and weeks before private contractors might have been available.

A portion of Royal Palms Parkway from Belle Terre Parkway to Rickenbacker Drive was closed on Sept. 16 after a contractor reported that a stormwater pipe beneath the road collapsed while maintenance was being completed. Traffic traveling eastbound from US-1 had to be detoured to Rickenbacker Drive to reach Belle Terre Parkway.

An emergency structural repair was required and the city’s Stormwater and Engineering department began seeking contractors to complete the hazardous work as quickly as possible. Unfortunately, the contractors would not have been able to begin work immediately, which would have caused an extended delay in the road closure.

The city’s Stormwater Pipe Crew has the experience to complete this type of work and offered to come forward and complete the job in a timelier manner. The crew estimated that it would take two weeks to complete the work. They began on Monday, Sept. 27 and the road was re-paved and re-opened on Friday, Oct. 1.

“The guys out here and their devotion has been very impressive,” Stormwater Pipe Supervisor Kevin Nelson said. “The whole teamwork dynamic out here has been incredible. We appreciate you guys being patient with us.”

In order to complete the job as efficiently as possible, the crew worked 12 hours per day. The crew rented a Caterpillar 336 Excavator and 16,000 pound trench boxes for the project and had 200 tons of base and 100 tons of rock delivered to the site.

“We’re very proud of the team for coming together and taking on a project that could have taken up to a month to complete and accomplishing it in just five days,” Interim City Manager Denise Bevan said. “I think this is a great testament to the quality of individuals who serve the citizens of Palm Coast and I couldn’t be more encouraged by their hard work and tenacity.” 

The road was paved early Friday morning and will be striped over the weekend. The road is now re-opened to traffic. The city of Palm Coast appreciates the community’s patience with this unexpected project. Watch a video update here: https://youtu.be/DybGDsIB4C0

 

Latest News

×

Your free article limit has been reached this month.
Subscribe now for unlimited digital access to our award-winning local news.